What are the building permits for new construction in Mallorca?

In order to build a new home on the island you will need to obtain building licences in Mallorca, as well as to know the regulatory framework.

Updated on November 10, 20265 min readBy the Armalutx Construction Team

What are the building permits for new construction in Mallorca?

To build a new home on the island, you will need to obtain the necessary building licences in Mallorca and, secondly, understand the regulatory and legal framework that governs the construction of new homes in the Balearic Islands, and specifically on the island of Mallorca.

Read on to find out what licences you need to build a home in Mallorca and what steps you need to follow to apply for them.

Law on New Construction in Mallorca

Before going any further, you need to know that new construction in Mallorca is regulated by:

Law 12/2017, of 29 December, on urban planning of the Balearic Islands (LUIB), which sets the requirements for building new buildings and regulates the granting of urban planning licences and their deadlines.

Furthermore, the Municipal Regulations of each municipality in Mallorca contain ordinances that may vary regarding fees, deadlines, and the documentation required. Therefore, we always recommend consulting the regulations of each specific municipality to learn about local specifics.

Planning licence: the licence you need to build a new home in Mallorca

The planning licence (what used to be called a «major works» licence) is the one you need for any project that involves building a new property or permanent structure (a detached house, a commercial building…)

The planning licence is applied for at the relevant town council. The documents to be submitted with the application are the following:

  • A complete technical project prepared by a certified architect, which must include detailed architectural plans, a descriptive report, structural calculations, and technical specifications.
  • The Material Execution Budget (PEM): this is the detailed estimate of the cost of the works. This budget does not include VAT, professional fees or other indirect costs. It is the basis for the municipal taxes on the licence, which vary from one municipality to another: in Palma, in 2026, ICIO is 4% and the planning fee 2.61%, half of which is deducted from the ICIO, so the total comes to around 5.3% of that budget; in Inca, ICIO is 3%.
  • Legal documentation such as proof of land ownership or owner authorisation.
  • Environmental Impact Study: Depending on the municipality and the characteristics of the project, you may need to submit this report, which evaluates the environmental impact of the new construction.
  • Certificates and other additional reports: Depending on the project, additional reports may be required. The geotechnical study is not optional: the Technical Building Code requires it in the initial phase of the project, before calculating the structure.

These documents would demonstrate the technical, legal, and economic viability of your project. The relevant municipal authority will then evaluate the project using this documentation and grant the planning licence.

Planning licence in Mallorca: what is the procedure?

First, you must submit the application to the city council of the municipality where you want to build. Generally, you can do this online, although in some municipalities, this process may not yet be available online and you may need to attend in person.

You will need to submit your town council's specific application form together with the documentation requested (the documents mentioned in the previous section). When the works are finished, the next step is the first occupation licence, granted by the town council. Since May 2024 it has replaced the first occupation certificate in the Balearic Islands, and the habitability certificate in Mallorca is now only applied for to renew it after 10 years.

Remember that each municipality may have specific additional requirements, so we recommend checking local regulations.

Once the application has been submitted, the town council has 3 months to decide from the date the file is complete and, if it meets all the requirements and the fees have been paid, it will issue the planning licence. For a new build, if it does not reply within that period, the licence is not deemed granted: silence counts as refusal. Unless the general plan says otherwise, the licence gives a maximum of 6 months to start the works and 3 years to finish them, extendable by half of those periods.

Particularities at the Municipal Level regarding Building Permits in Mallorca

As we've already mentioned, although the general regulations apply to all of Mallorca, each municipality may have additional requirements for processing building licences in Mallorca.

Therefore, we recommend that you review local regulations before starting your project. This includes the General Urban Development Plan (PGOU).

Your project will need to adapt to local limitations in terms of buildability, density, aesthetics, and other technical aspects.

Remember that fees and deadlines vary from municipality to municipality. Therefore, we recommend contacting the municipal administration for detailed information.

What are the consequences of building in Mallorca without a licence?

We do not recommend undertaking any new construction in Mallorca without the proper permit, as the consequences could be serious:

  • Firstly, you would face financial penalties and high fines, as it is a serious urban planning violation (very serious in protected rural land), with fines of 50 to 100% of the value of the work in urban land and up to 300% in protected rural land.
  • Secondly, you could be forced to demolish the work or have to regularize it through a new procedure, which would entail additional costs and delays.
  • Finally, you should know that a home built without a permit would have significant difficulties registering with the Property Registry. This means that both the sale and financing of the property would be very difficult.

Obtaining a building licence in Mallorca is not only required by law, but also offers several benefits, such as:

  • Ensure that the work is carried out in accordance with the law, which provides legal certainty and avoids penalties.
  • Greater equity value and greater ease for future transactions or financing.

A family of builders in Mallorca since 1967

At Armalutx, a construction company in Mallorca with a family trade since 1967, we are dedicated to construction of new housing in Mallorca. If you are interested in starting a new-build project, contact us today and ask for your personalised quote. And if the project is a development, it is worth knowing what Law 4/2025 allows to be built in the Balearic Islands and how long that route remains open.

We'll be happy to answer any questions you may have about building licences in Mallorca.

Armalutx Construction Team Construction company with an office in Inca that works throughout Mallorca: new construction, renovations, rehabilitation and structural reinforcements. Who we are.

Your work in Mallorca

Shall we talk about your project?

We'll visit you, see the work, and give you a detailed, no-obligation quote.