Do you need an architect or a construction company for renovations in Mallorca?
Architect vs construction company in Mallorca: what each one does, when is an architect mandatory, the 3 contracting models and fees.

The most frequently asked question when planning a renovation in Mallorca is a bit of a trick question: in most cases, it's not "architect or construction company," but rather "which combination of the two is best for you." For a complete renovation, an extension, or any work involving the structure, layout, or general installations, the Balearic Islands' Urban Planning Law 12/2017 requires a technical project signed by a registered architect and on-site supervision during construction. For a minor renovation (painting, replacing flooring, a bathroom renovation without affecting general installations), a construction company is sufficient. This guide helps you decide which option applies to you, the cost of each, and how to avoid the most expensive mistakes.
The wrong question: if the works need a project, you need both
Many people come to this decision thinking they have to choose one of the two to save money. In reality, architects and builders do completely different jobs, and when the works need a technical project (as many full renovations do), the architect is not optional: the law requires one.
- The architect designs, calculates, technically directs and certifies.
- The construction company executes what the architect has designed, under his direction.
They are not substitutes. They are complementary parts of the same process. What you can choose is how to hire them: in parallel (each on their own), or in an integrated way (the construction company brings in the architect as a collaborator). We explain this in more detail in the models section.
What exactly does an architect do in a renovation?
The architect is involved in five specific stages. If the works need a project, they cannot be skipped:
- Preliminary project: initial study of the current state, distribution proposal, initial quality decisions and cost guidance.
- Approved technical project: final plans, technical report, compliance with the Technical Building Code (CTE), structural calculations, urban planning justification. This document is submitted to the city council to obtain a building licence.
- Licence processing: although the architect signs the project, the practical processing is usually coordinated by the construction company or a manager — but the technical document belongs to the architect.
- Project management: periodic site visits (weekly or bi-weekly depending on complexity), validation of modifications, quality control and signing of the order book.
- Final work certificate: a document that certifies that the work has been carried out according to the project specifications. Without this certificate, modifications cannot be registered, nor can new utilities be connected.
In works with a project, the technical architect (aparejador) is also compulsory: they direct the execution of the works, coordinate the trades and oversee health and safety on site. The technical architect's fees are usually 30-40% of the architect's and are contracted alongside them.
What exactly does a construction company do?
The construction company is the one that physically carries out the work. Its specific responsibilities are:
- Provision of materials according to the technical project.
- Management and coordination of trades: bricklayers, plumbers, electricians, carpenters, painters, air conditioning installers.
- Material execution in accordance with the plans and technical specifications of the project.
- Compliance with the work schedule agreed upon in the contract.
- On-site quality control and defect correction.
- Assumption of the legal guarantees LOE: 1, 3 and 10 years depending on the type of damage.
- Final cleaning, facility testing and handover.
A reputable construction company doesn't make substantial changes on its own—it proposes them to the architect and the client, they are documented and signed before construction begins. We have a more detailed analysis of the criteria for identifying a reputable construction company in our guide on how to choose the best construction company in Mallorca.
The 3 possible models for renovation in Mallorca
This is the real decision. There are three ways to hire, each with its own specific advantages and disadvantages:
| Model | How it works | Advantages | Disadvantages |
| A. Architect and construction company separately | You hire an architect. He creates a project. You request quotes from several construction companies based on that project. You choose one. | Technical independence of the architect. You compare budgets with equal bases. | Coordination is your responsibility. Risk of friction between architect and construction company. Longer deadlines. |
| B. Only construction company | You hire a construction company directly without a technical project. | Cheaper and faster. | Only legal for works that do not need a project. If the works need one, it is illegal and they can be stopped. |
| C. Construction company with collaborating architect | You hire the construction company. They offer you a collaborating architect they regularly work with. You sign two contracts (one with each architect), but the construction company handles the coordination. | Smooth coordination, shorter deadlines, architect who knows the construction company's execution standard. | If the architect-builder relationship is not honest, there may be a conflict of interest in budgets. |
At Armalutx, we offer models A and C: we work with your architect if you already have one, and if not, we recommend collaborating architects we've worked with for years. In both cases, the architect's contract is directly between you and them—we don't invoice their fees, so there's no financial conflict of interest.
When is an architect mandatory: the Balearic legal framework
The Balearic Islands Urban Planning Law 12/2017 (LUIB) and municipal ordinances classify construction projects into two main groups. The difference is crucial:
- Planning licence: required for works that touch the foundations or the load-bearing structure (pillars, girders, beams, floor slabs, load-bearing walls and making or closing openings in them), extensions, changes of use, works that change the number of homes and any intervention that needs a project under the Spanish Building Act (LOE). In residential buildings, that project is signed by an architect.
- Prior notification: required for small-scale works that do not need a project, such as painting, replacing floors, kitchen units or sanitaryware, and minor repairs. In Palma, if the works move partition walls or change the façade without touching the load-bearing structure, the notification is signed by a technician and the works start after 15 days; the simple version lets you start the next day. We explain it in prior notification of building works in Palma.
The line between one and the other isn't always obvious. That's why it's important to consult with the local council or a qualified professional before starting—construction begun without the proper permit can be halted and penalized with fines that, in urban areas, range from 50% to 100% of the construction's value, and never fall below €600. We delve deeper into this topic in our guide on building licences in Mallorca.
How much does an architect cost: real fees in 2026
Architect fees are calculated based on the Construction Cost Estimate (PEM) of the project, not the total budget. These are the fee ranges in effect in 2026 for renovations in Mallorca:
| Architect's service | Fees on PEM | Example PEM €60,000 |
| Basic technical project only | 4 – 6% | €2,400 – €3,600 |
| Technical project + construction management | 6 – 9% | €3,600 – €5,400 |
| Project + management + interior design | 9 – 14% | €5,400 – €8,400 |
| Quantity surveyor (construction management) | 2 – 4% | €1,200 – €2,400 |
| Endorsement by the Official Association of Architects | 0.5 – 1.2% | €300 – €720 |
Adding up the project, site supervision, the technical architect and the endorsement, the full technical fees for a renovation with a construction cost of €60,000 come to between 9% and 14% of that cost, i.e. €5,400–€8,400. It sounds a lot until you compare it with the cost of a large job that has been badly designed and has to be partly redone, which can double or triple the spend.
Typical mistakes when hiring a bad architect and construction company
These are the five most common mistakes we see from clients who come to us with the project already underway or with problems:
- Starting without a technical project works that need one, to «save on architect's fees». The council stops the works at the first complaint from a neighbour. Fines, an indefinite stoppage and the obligation to regularise afterwards (which costs twice as much).
- Hiring an architect and a construction company without prior coordination. The architect creates a project that the construction company considers unworkable or overpriced, and vice versa. Constant arguments and missed deadlines.
- Accepting a construction company's quote based on an incomplete project. The price systematically increases because each undetailed item is charged as an "extra.".
- Don't stipulate in the contract who decides what. It must be clearly stated in writing who approves project modifications, material quality, and timelines. Without that, everyone will act in their own self-interest.
- Forgetting the technical architect. In works with a project, one is compulsory. Without one, the site supervision is invalid and the completion certificate may be blocked.
If your renovation is of a flat in Palma or anywhere else on the island, it is also worth reading our specific guide to flat renovations in Mallorca, where we explain the whole process and how an itemised quote reduces many of these risks.
Recommendation based on your type of renovation
To help you make a quick decision, here is our honest criterion based on the type of work:
- Cosmetic renovation without affecting general installations (painting, laminate flooring, furniture replacement): construction company only. No technical project required. Prior notification to the city council is required if the interior facade is affected.
- Kitchen or bathroom renovations without affecting the building's main utilities: only contractors with proven technical experience are permitted. Prior notification or a minor permit may be required depending on the municipality.
- Complete apartment renovation including layout change, new installations and/or windows: architect + surveyor + construction company. Model A or C according to your preference. Major licence required.
- Renovation involving modifications to load-bearing walls, expansion of surface area, or change of use: architect + building engineer + construction company with structural experience. Model C usually works best due to the intensive coordination it requires.
- Change of use from commercial premises to residential: architect + technical architect + specialised construction company. Complex urban planning procedure, best with a coordinated team from the start.
Whenever you need a construction company, what we cover at Armalutx is set out on our page for construction company in Mallorca, including how we prepare the quote and the guarantees provided by the Spanish Building Act (LOE). And in our page on home renovations in Mallorca we explain how we organise a renovation.
Frequently Asked Questions
Can I carry out a renovation that needs a project without hiring an architect?
No. The Spanish Building Act (LOE) requires a project for interventions that change the structural system as a whole, the volume, the external appearance or the use of the building, and in residential buildings that project is signed by an architect, with site supervision during the works. Works that do not need one, such as changing finishes or moving a partition wall, do not require an architect, although in Palma moving partition walls requires a technician to sign the prior notification. Carrying out works that need a project without one can end in a stoppage, a fine and the obligation to regularise afterwards.
Who hires the technical architect: me or the architect?
You hire them directly, just like you would the architect. The technical architect (technical architect) signs off on the construction management and is usually recommended by the architect. Their fees are paid separately. In some cases, the architect and the technical architect work in the same firm and offer both services together.
If a construction company tells me that it takes care of "everything," including the architect, is that okay?
It depends. If she's offering to introduce you to a collaborating architect with whom you sign a direct contract, perfect—that's model C. If she's offering to invoice the architect's fees herself without you signing anything with him, that's bad: you're losing technical independence and you don't have a direct point of contact with the project manager. Ask to see the architect's contract.
How long does it take to obtain a planning licence in Mallorca?
The law gives municipalities three months from the date the file is complete, but the actual timeframes vary considerably: in Palma, the City Council estimated the average time to be between 9 and 12 months in February 2026, and with a collaborating entity (ECU), between one and three months. Law 4/2025 does not change these timeframes for renovations or housing projects; it only accelerates strategic residential projects.
Can I change construction companies mid-construction if I'm not happy?
Technically, yes, but it's a complicated and expensive process. It involves terminating the contract (with potential compensation claims), drawing up a progress report with the architect, assessing what has been completed and what remains to be done, and hiring a new construction company. The new construction company usually charges extra for taking over a project already underway and assuming the work done by the previous contractor. The sensible thing to do is choose carefully from the outset—verify references, budget templates, and legal guarantees before signing.
Request a consultation with no obligation.
If you are planning a renovation in Mallorca and are not sure whether you need an architect or just a builder, call us on +34 625 16 47 18 or email info@armalutx.com. On the first visit we assess the scope of the works and tell you frankly whether a prior notification is enough or a licence is needed, and which professionals you need. No obligation. If your works need a project and you ask us to arrange it, we put you in touch with architects we have worked with for years — you sign the contract directly with them.
Armalutx Construction Team Construction company with an office in Inca that works throughout Mallorca: new construction, renovations, rehabilitation and structural reinforcements. Who we are.