In Palma there is no such thing as «minor works» or «major works»: there is prior notification and there is a planning licence. Prior notification covers small-scale works and those that do not touch the building's load-bearing structure. It is filed through the City Council's online portal together with the quote and proof of payment of the planning fee (2.61%) and the ICIO construction tax (4%), and lets you start the next day or, if a technician is needed, after 15 days. Anything that touches pillars, girders or load-bearing walls, extends the house or changes its use needs a licence.
Every week someone who is about to renovate in Palma rings us with the same question: «is this minor or major works?». The short answer is that in Palma that question no longer exists. The City Council's online portal has only two building procedures: «Obras.01 – Comunicación previa» (prior notification) and «Obras.02 – Licencia urbanística» (planning licence). Knowing which one your renovation needs is what decides whether you start next week or many months from now.
What prior notification is and how it differs from a licence
With a prior notification you do not ask for permission: you tell the City Council that you are going to carry out works, submit the documents required and, once the waiting period is over, you can start without waiting for a reply. The City Council can check it afterwards and, if something is missing or the works do not match what was notified, stop them.
With a planning licence it is the other way round: you submit the project and cannot start until the City Council grants it. The legal deadline is three months from the date the documentation is complete, but in Palma the real average time for planning licences is currently between 9 and 12 months. Through an accredited collaborating body (ECU), which is optional and paid for, the City Council has granted licences in one to three months.
That is why it is worth knowing which side your works fall on before the quote is drawn up.
Which works go through prior notification in Palma
The municipal document «Tipos de obras, documentación a presentar e inicio de obra» (types of works, documents to submit and start of works) sets out several types of prior notification. For a home renovation, two of them matter.
Simple prior notification
It covers works of simple technique and minor construction scale that do not need a project. This usually includes renovations that renew without moving anything:
- Replacing floors, tiling and wall finishes.
- Renovating a bathroom or a kitchen without moving partition walls.
- Replacing sanitaryware, kitchen units or the installations inside the home.
- Painting or repairing interior finishes.
You can start the works the day after filing it.
Prior notification with a technician
It covers works that partly affect the structure (for example, partial intermediate floor slabs), the exterior design, habitability or safety, provided they do not touch the load-bearing structure (pillars, girders, load-bearing walls), do not extend the home, do not change its use and do not reconfigure more than 60% of its floor area. Scaffolding on the façade is also included here.
- Moving or knocking down partition walls to change the layout.
- Replacing exterior windows and doors, which the City Council treats as exterior design.
- Works that improve habitability or safety without touching pillars or load-bearing walls.
It must be filed with a technician who takes responsibility for the works, a report with the construction cost estimate and drawings of the current and the renovated layout. The works can start 15 calendar days after filing it.
Works that need no procedure at all
The Balearic Islands Planning Act (art. 145.2.a) exempts from any procedure small-scale works on urban land costing less than 3,000 euros that need neither a project nor technical supervision and are carried out entirely inside the building. Palma applies the same rule.
There are three important caveats:
- It does not apply to buildings of cultural interest (BIC), listed buildings or buildings that do not conform to current planning.
- You cannot split the works to stay under the limit: works in the same place and year are added together.
- No procedure does not mean no rules. If you live in a flat, the owners' association must be informed, and the works cannot cause more disturbance than the noise and working-hours bylaws allow.
When you need a planning licence in Palma
Prior notification stops being enough as soon as the works touch what holds the building up or change what it is. You need a planning licence for:
- Works affecting the foundations or the load-bearing structure: pillars, girders, main beams or load-bearing walls.
- Extensions, new storeys and any works that change the volume.
- Works that change the number of homes or commercial premises.
- Changes of use, such as converting commercial premises into a home.
- Renovations that reconfigure more than 60% of the floor area.
- Any intervention that, under the Spanish Building Act (LOE), needs a project. In residential buildings, that project is signed by an architect.
New-build works, demolitions and structural reinforcement also always need a licence.
Which documents you need to submit
For a simple prior notification:
- The prior notification form from the online portal.
- A site location plan.
- Photos or a drawing of the area where the works will take place.
- A description of the works.
- An itemised quote.
- Proof of payment of the fee and the ICIO.
For prior notification with a technician, you also add the document of the technician who takes responsibility for the works, the report with the construction cost estimate and drawings of the current and the renovated layout.
It is filed through the City Council's online portal or at a Citizen Service Office. Companies and registered professionals must file online.
How much it costs: fee and ICIO
Prior notification pays the same as a licence, and you pay when you file it:
- Planning fee: 2.61% of the actual cost of the works.
- ICIO (construction tax): 4%. Since late October 2025, half of the planning fee already paid is deducted from the ICIO.
In practice, the two together come to around 5.3% of the cost of the works. There are ICIO rebates for specific works: 25% for works whose only aim is to improve energy efficiency and 90% for accessibility works, among others. And the planning fee is halved for building rehabilitation works and for listed buildings.
That is why the quote you submit has to be real and itemised: it is the basis on which both are calculated.
When you can start and how long you have
- Simple prior notification: the day after filing it.
- Prior notification with a technician: after 15 calendar days.
- Deadline to finish: the form sets a maximum of two years, which can be extended by one more.
If something turns up during the works that changes their scope, such as a beam that needs reinforcing, the notification you filed no longer covers the works and you must file whatever applies before carrying on.
Historic centre and listed buildings
Here everything takes longer. For a prior notification in a listed building or in the historic centre, the municipal document requires prior authorisation from the Island Heritage Commission of the Consell de Mallorca and a historical and artistic study. In addition, the works covered by article 287 of the General Plan need a favourable report from the Historic Centre and Catalogue Commission before they can start.
Municipal rules do not fully agree on this point: the 2023 General Plan says that prior notification cannot be used for listed buildings and buildings of cultural interest (BIC). If your building is protected, check with the Planning Department before taking anything for granted. We explain this in more detail in how to renovate an old building in Palma.
Skips, scaffolding and street occupation
Prior notification does not let you put a skip on the street. To occupy the public highway (skip, rubble bag, scaffolding, fencing or materials) you need a separate permit, the «Licencia de ocupación de la vía pública por razón de obras» (licence to occupy the public highway for works):
- It must be requested at least 72 working hours in advance.
- You must attach the licence or the prior notification for the works.
- It costs €0.41 per square metre per day, and the days run consecutively, public holidays included.
- A skip or a rubble bag also needs a loading and unloading bay for the same period.
Plan material deliveries and rubble removal so that the street is occupied for as short a time as possible.
Frequently asked questions about prior notification in Palma
Do I need a licence to renovate my bathroom or kitchen in Palma?
Usually not. If you are replacing finishes, sanitaryware, units and installations without moving partition walls or touching the structure, a simple prior notification is enough and you can start the next day. If you also move partition walls, it becomes prior notification with a technician. You only need a licence if the works touch a load-bearing wall or the load-bearing structure.
Is changing the layout of a flat prior notification or a licence?
If you move partition walls without touching pillars, girders or load-bearing walls and the new layout does not affect more than 60% of the floor area, it is prior notification with a technician: a technician signs and you wait 15 days. If a load-bearing wall is removed or more than that 60% is reconfigured, you need a planning licence.
Can you replace the windows with a prior notification?
Yes, usually through prior notification with a technician, because replacing exterior windows and doors affects the design of the façade. In a listed building or one in the historic centre, or if you change the size of the opening, check with the Planning Department first.
What happens if I carry out the works without filing prior notification?
It is a planning offence. The City Council can stop the works, require you to legalise them and open disciplinary proceedings. It can also cause problems when you sell the flat or apply for the first occupation licence or the habitability certificate.
Can the company doing the works file the prior notification?
Yes. It can be filed by the owner or by someone on their behalf, and companies always do it through the online portal. What matters is that the description and the quote match the works that will really be carried out.
We tell you which procedure your works need before we start
At Construcciones Armalutx, a family of builders since 1967, we look at the works and tell you which procedure applies: whether prior notification is enough, whether it needs a technician or whether a licence is required. We file it before we start and build it into the works schedule. If you are thinking about renovations in Palma de Mallorca, tell us about your project on 625 16 47 18 or at info@armalutx.com. You can also see how we approach flat renovations in Mallorca.